Our Projects
CONSULTANCY SERVICES FOR CARRYING OUT GEOTECHNICAL INVESTIGATION OF RUEMBE BRIDGE IN KILOSA DISTRICT COUNCIL.
CONSULTANCY SERVICES FOR CARRYING OUT GEOTECHNICAL INVESTIGATION OF RUEMBE BRIDGE IN KILOSA DISTRICT COUNCIL.
Location within the Country: Morogoro (Kilosa District)
Name of the Client: TARURA – Reginal Manager
Start date 07/2021
Completion Date: 10/2021
Duration of Assignment: 02 Months
Narrative Description of Project:
The main purpose of the ground investigation was to have a clear appreciation of the mechanical and physical properties of the soil strata on which the foundations of the bridge are designed to be installed.
Services Provided by Advanced Engineering Solutions:
- Drilling 4 boreholes within the proposed site to a maximum of 25 m depth.
- Performing SPT for soil strata and computing RQD for rock strata found in the borehole.
- Collecting the disturbed and undisturbed samples at appropriate intervals.
- Recording water table level.
- Logging the profiles on each borehole.
- Taking photographs of the profile on each borehole.
- Performing laboratory tests on samples obtained from the site.
- Analyzing and reporting the geotechnical findings.
CONSULTANCY SERVICES FOR CARRYING OUT GEOTECHNICAL INVESTIGATION OF MJONGA BRIDGE IN MVOMERO DISTRICT COUNCIL.
CONSULTANCY SERVICES FOR CARRYING OUT GEOTECHNICAL INVESTIGATION OF MJONGA BRIDGE IN MVOMERO DISTRICT COUNCIL.
Location within the Country: Morogoro (Mvomero District)
Name of the Client: TARURA – Reginal Manager
Start date 07/2021
Completion Date: 09/2021
Duration of Assignment: 02 Months
Narrative Description of Project:
The main purpose of the ground investigation was to have a clear appreciation of the mechanical and physical properties of the soil strata on which the foundations of the bridge are designed to be installed.
Services Provided by Advanced Engineering Solutions:
- Drilling 4 boreholes within the proposed site to a maximum of 14.5 m depth.
- Performing SPT for soil strata and computing RQD for rock strata found in the borehole.
- Collecting the disturbed and undisturbed samples at appropriate intervals.
- Recording water table level.
- Logging the profiles on each borehole.
- Taking photographs of the profile on each borehole.
- Performing laboratory tests on samples obtained from the site.
- Analyzing and reporting the geotechnical findings.
ENVIRONMENTAL AUDIT FOR THE EXISTING INCINERATOR OF AGA KHAN HOSPITAL LOCATED AT SEA VIEW STREET, KIVUKONI WARD, ILALA MUNICIPALITY IN DAR ES SALAAM CITY
ENVIRONMENTAL AUDIT FOR THE EXISTING INCINERATOR OF AGA KHAN HOSPITAL LOCATED AT SEA VIEW STREET, KIVUKONI WARD, ILALA MUNICIPALITY IN DAR ES SALAAM CITY
Location within the Country: Dar es Salaam
Name of the Client: Aga Khan Hospital
Start date 03/2022
Completion Date: Ongoing
Duration of Assignment: 6 Months
Narrative Description of Project:
The core operation activity in the audited project is the incineration of the healthcare waste generated from the Hospital
Services Provided by Advanced Engineering Solutions:
- To examine current environmental practices, health and safety practices of the Incinerator
- To provide a comprehensive description of the activities, processes and operations including their potential impacts;
- To review and assess compliance with all relevant national and international environmental and labour policies, laws, licenses and regulations pertaining to waste management operations;
- To assess project strengths and weaknesses during the operation
- To propose practical enhancement and mitigation measures for the identified positive and negative impacts associated with the incineration of healthcare waste;
- To develop an implementable Environmental and Social Management Plan (ESMP) and Environmental Monitoring Plan (EMP) for the project.
- To propose a preliminary, decommission plan for the incinerator
- To propose recommended action toward project weaknesses
Consultancy Services for Supervision of Upgrading of Tabora – Koga – Mpanda Road (354 km) to Bitumen Standard: Lot 1: Tabora – Sikonge (Usesula) Section (30 km).
Location within the Country: Tabora
Name of the Client: TANROADS – Headquarters
Start date 03/2015
Completion Date: 11/2018
Duration of Assignment: 32 Months
Name of Associated Consultant:
AARVEE Associates Architects Engineers & Consultants PVT LTD [India]
Narrative Description of Project:
The project is part of 354 km upgrading of Tabora-Koga-Mpanda road; Lot 1: involves upgrading 30 km section from Tabora-Sikonge.
Services Provided by Advanced Engineering Solutions:
1. Preparation and approval of Quality control and quality assurance plan
2. Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
3. Review of pavement design
4. Mix design of stabilized material, asphalt concrete, cement concrete
5. Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
6. Preparation of monthly report
7. Reviewing and approving Contractor’s quality assurance plan
8. Implementation of contractor’s environmental management plan
Consultancy Services for Detailed Design and Preparation of Tender Documents for Assorted Accident “Black Spots” Interventions Measures and Supervision of Improvement of Assorted Accident “Black Spots” Along Dar es Salaam Corridor
Location within the Country: Along Dar-es-salaam Corridor (Coastal region, Dar-es-salaam, Morogoro, Mbeya)
Name of the Client: TANROADS – HQ
Start date: Nov. 2015
Completion Date: ongoing
Duration of Assignment: 35 Months
Name of Associated Consultant: LEA Associates (Lead Consultant)
Detailed Narrative Description of Project:
The objective of the project is to carryout Detailed Design and Preparation of Tender Documents for the accident “black spots” priority interventions measures and Supervision of its implementation along the Dar es Salaam Corridor. Sections covered includes: Dar es Salaam – Kidika (400 km); Igawa – Mbeya (117 km); Mbeya – Tunduma (103 km) and Mbeya – Kasumulu (117 km). The work involves design of 36 Nos accident “black spots” identified in the initial Road safety assessment.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Traffic count and traffic analysis
4.Pavement design
5.Detailed engineering Design
6.Construction supervision
7.Preparation of Detailed Engineering design report
8.Preparation of bill of quantity
9.Preparation of contract documents
Consultancy services for the Supervision for Upgrading of Tabora – Koga – Mpanda Road to Bitumen Standard, Lot 1: Usesula – Komanga Section (108 km), Sikonge Spur 2.21 km & Sikonge Town Section 7.36 km
Location within the Country: Tabora
Name of the Client: TANROADS – Headquarters
Start date: Dec. 2017
Completion Date: ongoing
Duration of Assignment: 36 Months
Name of Associated Consultant:
LEA International Ltd (Canada) in JV with LEA Associates South Asia Pvt. Ltd (India)
Detailed Narrative Description of Project:
The Government’s [of the United Republic of Tanzania] efforts to vitally link the significant Regions of Tabora and Katavi as manifested through the upgrading of the Tabora – Koga – Mpanda Road to bitumen standard is packaged with Lot 1 of Usesula – Komanga Section [108 Km], Sikonge Spur of 2.21 Km and Sikonge Town Section of 7.36 Km.
Advanced Engineering Solutions, in association [as a Sub-Consultant] with LEA International Ltd [Canada] in JV with LEA Associates South Asia Pvt. Ltd [India], is taking a weighty role in supervision of the said package. It is highly counted-on that after the completion of the works the initially far-fetched areas to-be connected by the section will be all-weather get-at-able.
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Supervision of construction of drainage structures
3.Traffic count and traffic analysis
4.Mix design of stabilized material and cement concrete
5.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1],
6.crushed base [CRR] and Marshal asphalt concrete
7.Preparation of monthly report
8.Reviewing and approving Contractor’s quality assurance plan
9.Implementation of contractor’s environmental management plan
Consultancy Services for Carrying out Feasibility Study, Detailed Engineering Design and Preparation of Tender Document for Upgrading to Double Surface Dressing of Magu – Bukwimba – Ngudu – Hungumalwa Road [71 Km] in Mwanza Region
Location within the Country: Mwanza
Name of the Client: TANROADS – Mwanza
Start date Sept 2017
Completion Date: June 2019
Duration of Assignment: 8 Months
Name of Associated Consultant: Lidwala Consulting Engineer of South Africa (Associate Consultant)
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to do the feasibility study
of the road, environmental and social impact assessment and provision of engineering
services for design and detailing the road and preparation of tender documents.
The project also included design of several drainage structures (Box and pipe culverts),
geo-technical investigation and design of several bridges including;-CONCRETE BRIDGE, Two Spans [35.0 m each]
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Pavement design
4.Detailed engineering Design
5.Preparation Detailed drawings
6.Preparation of Detailed Engineering design report
7.Preparation of bill of quantity
8.Preparation of contract documents
Consultancy Services for Provision of Topographical Survey and Geotechnical Survey for the Proposed Zanzibar New City Centre at Kwahani and Chumbuni-Zanzibar
Location within the Country: Zanzibar, Tanzania
Name of the Client: ZSSF
Start date: July 2018
Completion Date: Feb 2019
Name of Associated Consultant: Geoprimosi Company Ltd, Tanzania
Detailed Narrative Description of Project:
The consultant’s task is to perform Geotechnical Investigations and topographical survey
at the proposed project location to ascertain the characteristics of actual soil, and the
engineering properties of each soil for the design of the foundation and submit recommendations for types of foundations and safe bearing pressure for the foundation design.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Preparation of Draft geotechnical investigation report
3.Preparation of final geotechnical investigation report
Consultancy Services for Feasibility Study, Environmental Social Impact Assessment [ESIA], Detailed Engineering Design and Preparation of Tender Documents for Upgrading of Matomondo – Mlale Road (23km) in Songea District to Bitumen Standard.
Location within the Country: Songea, Ruvuma
Name of the Client: TARURA – Headquarters
Start date: March 2019
Completion Date: Sept. 2019
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to undertake Feasibility Study,
Environmental & Social Impact Assessment [ESIA],
Detailed Engineering Design and Preparation of Tender Documents for Upgrading
of Matomondo – Mlale Road (23km) in Songea District, in Ruvuma region to Bitumen Standard
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Feasibility Study including preliminary design, economic analysis and cost estimates;
3.Preliminary Environmental and Social Impact Assessment (ESIA), Preliminary Resettlement Action Plan (RAP) and survey of properties to be affected;
4.Detailed engineering design and cost estimates;
5.Detailed ESIA and RAP;
6.Preparation of Tender Documents.
Consultancy Services for Detailed Engineering Design of the access road for 400/220 kV New Arusha
Location within the Country: Arusha, Tanzania
Name of the Client: TANESCO-ARUSHA
Start date: Oct 2018
Completion Date: Jan 2019
Duration of Assignment: 3.6 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to do the Detailed Engineering Design
and preparation of tender documents of the access road for 400/220 kV New Arusha.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Draft Detailed engineering design Report and Bills of Quantities (including Material report and Engineering Drawings)
3.Final Detailed engineering design Report and Final Bills of Quantities (including Material report and Engineering Drawings)
Consultancy Services for Provision of Consultancy Services for Feasibility Study and Preliminary Design for Dodoma Capital City Commuter Trains Services.
Location within the Country: Dodoma, Tanzania
Name of the Client: TANZANIA RAILWAYS CORPORATION
Start date: Nov. 2018
Completion Date: ongoing
Duration of Assignment:9.5 Months
Name of Associated Consultant:
Ardanuy Ingunieria S.A; Soosung Engineering Co. Ltd; International Consultants and Technocrats Pvt. Ltd
Detailed Narrative Description of Project:
With due regard to the fact that the Government of the United Republic of Tanzania
recognizes the need for the passenger transport services that will primarily operate
within the metropolitan area of the Capital City of Dodoma, connecting commuters
to a central city from adjacent suburbs or commuter towns; the Government had
decided to embark on the provision for the commuter rail transport system within
and around the Capital City towards realization of effective mobility, green transport
as well as deterring the eventual socio-economic repercussions of the anticipated
overcrowding. Advanced Engineering Solutions, in association [as a Sub-Consultant]
with Ardanuy Ingunieria S.A; Soosung Engineering Co. Ltd; International Consultants
and Technocrats Pvt. Ltd is privileged to got involved at the embryonic juncture of
providing consultancy services for the feasibility study and preliminary design for
Dodoma Capital City Commuter Trains Services of which after reification will pave
way towards setting the Capital City at a grandstand overlooking as well as
integrating with other Cities.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Draft Feasibility Study and Preliminary Design Report
3.Executive Summary report
4.Economic Study Report
5.Environmental Impact Assessment (EIA) and Mitigation plan (EMP report)
6.Social Impact Assessment (SIA) and Mitigation Plan (SMP) including the Preliminary Resettlement Action Plan (RAP) Framework document
7.Preliminary design report including, Materials/Soil Investigations report, Books of Drawings; and
8.The Work Space for HDM-4 Model used for economic analysis.
Consultancy Services for Supervision of Road Projects (Lot 1: Upgrading of 5.17km Roads to Bitumen Standard) Under ULGSP in Tabora Municipality
Location within the Country: Tabora
Name of the Client: Tabora Municipal Council
Start date 08/2016
Completion Date: 12/2018
Duration of Assignment: 12 Months
Narrative Description of Project:
The project provides for new construction/ upgrading/ of approximately of 1.06KM of urban roads to bituminous standard, including vertical and horizontal alignment design, pavement design, drainage structures
Services Provided by Advanced Engineering Solutions:
1. Preparation and approval of Quality control and quality assurance plan
2.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
3. Review of pavement design
4. Mix design of stabilized material, asphalt concrete, cement concrete
5. Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
6. Preparation of monthly report
7. Reviewing and approving Contractor’s quality assurance plan
8.Implementation of contractor’s environmental management plan
Consultancy Services for Construction Supervision of New Wami Bridge (513.5m) and its Associated Approach Roads (4.325km)
Location within the Country: Chalinze (Coast Region), Tanzania
Name of the Client: TANROADS – Headquarters
Start date: March 2019
Completion Date: March 2021
Duration of Assignment: 24 Months
Name of Associated Consultant: Ilshin Engineering & Consultants [South Korea]
Detailed Narrative Description of Project: The project involves supervision of the construction of a cast-in-situ Balanced Cantilever Bridge 513.50m long. The total design length of the project road including structure is about 4.325 km connecting Chalinze to Segera. Due to the substandard geometry of the existing bridge caused by the complicated landscape of the area, the location of the New Wami Bridge has been proposed to be on the downstream direction of the existing structure. The project also required design review of bridge, road and associated relief drainage structures. The review of design includes review of bridge design, review of the road design which includes vertical and horizontal alignment design, pavement design, drainage structures, structural designs for flood control structure
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Bridge design review
3.Review of geometrical and profile design
4.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
5.Review of pavement design
6.Mix design of stabilized material and cement concrete
7.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1],
Consultancy Services for Detailed Engineering Design and Preparation of Tender Documents for Upgrading Nyasho – Majita road to Bitumen Standard [2.38 km]
Location within the Country: Musoma
Name of the Client: Musoma Municipal Council
Start date 04/14
Completion Date: 08/14
Duration of Assignment: 4 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The project involved designing of 2.380 km of urban road. The work also involved Pavement design capable of carrying 1-3 Million Equivalent Standard Axle, geometrical design, and pavement design capable of carrying 1-3 Million Equivalent Standard axles, traffic analysis, hydraulic /hydrology analysis and design of drainage structures.
Services Provided by Advanced Engineering Solutions:
1. Preparation of inception report
2. Materials investigation and preparation of materials report
3. Traffic count and traffic analysis
4. Design of all drainage structures
5. Pavement design
6. Topographical surveying and creation of digital terrain model [DTM] using commercial software
7. Preparation of Detailed Engineering design report
8. Preparation of bill of quantity
9. Preparation of contract documents
Consultancy services for feasibility study, environmental social impact assessment, detailed engineering design and preparation of tender documents for construction of Nduruma (36m span) & Kimosonu (18m span) bridges along Kijenge – Usariver And Usariver – Oldonyosambu roads
Location within the Country: Arusha, Tanzania
Name of the Client: TANROADS – Arusha
Duration of Assignment: 5 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to conduct geotechnical investigations, conduct Feasibility study including preliminary environmental & social impact assessment and survey of properties to be affected by the construction works. Detailed Engineering Design, including Detailed Environmental and Social Impact Assessment, development of Resettlement Action Plan and preparation of bidding documents. The new bridges to be designed include;
-KIMASONU BRIDGE, One Span Concrete Bridge
-NDURUMA BRIDGE, Two Spans Concrete Bridge
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Geotechnical Investigation
3. Materials investigation and preparation of materials report
4. Pavement design
5. Detailed engineering Design
6. Preparation of Detailed Drawings
7. Preparation of Detailed Engineering design report
8. Preparation of bill of quantity
9. Preparation of contract documents
Consultancy Services for Detailed Engineering Design and Supervision for Rehabilitation of Selected Rural Roads in Kongwa District Council (69.8 Km) to Gravel Standard in the Financial Year 2015/2016.
Location within the Country: Kongwa, Dodoma
Duration of Assignment: 12 Months
Start date : Sept 2016
Completion Date: Oct 2018
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to provide an all-weather passable road segments on which the motoring public can travel in relative comfort and safety. The roads segments involved are from three wards; Mtanana, Kibaigwa and Njonge totaling a length of 69.8 Km. The roads include:
i. Mtanana – Makawa – 24.8 Km in Mtanana Ward
ii. Ugogoni – Kibaigwa – 30.0 Km in Kibaigwa ward
iii. Njonge – Makutupa – Ngese – 15.0 Km in Njoge ward
The project intends to increase access to markets in selected community agricultural commodities.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2. Materials investigation and preparation of materials report
3. Pavement design
4. Detailed engineering Design
5. Construction supervision
6. Preparation of Detailed Engineering design report
7.Preparation of bill of quantity
8.Preparation of contract documents
Consultancy Services for Carrying out Feasibility Study, Environmental and Social Impact Assessment (ESIA), Detailed Engineering Design and Preparation of Tender Document for Upgrading to Double Surface Dressing of Monduli – Engaruka (Ngaresh – Enguiki Section) (11 Km) in Arusha Region.
Location within the Country: Arusha, Tanzania
Name of the Client: TANROADS – Arusha
Start date: Nov 2018
Completion Date: July 2019
Duration of Assignment:5 Months
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to undertake Feasibility Study, Environmental and Social Impact Assessment, Detailed Engineering Design and Preparation of Tender Documents for Upgrading to double surface dressing of Monduli – Engaruka (Ngaresh – Enguiki section) (11 km) in Arusha region
Services Provided by Advanced Engineering Solutions:
1. Preparation of inception report
2. Feasibility Study including preliminary design, economic analysis and cost
estimates;
3. Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected;
4. Detailed engineering design and cost estimates;
5. Detailed ESIA and RAP;
Consultancy Services for Carrying Out Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Upgrading of Wenda – Mgama Road (19km) in Iringa District – Ihemi Cluster and Mtili – Ifwagi – Mkuta Road (14km) in Mufindi District – Ihemi Cluster to Appropriate Sealing Standard.
Location within the Country: Iringa, Tanzania
Name of the Client: TARURA – Headquarters
Start date: March 2019
Completion Date: Sept. 2019
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to undertake Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Upgrading of Wenda – Mgama Road (19km) in Iringa District – Ihemi Cluster and Mtili – Ifwagi – Mkuta Road (14km) in Mufindi District – Ihemi Cluster to Appropriate Sealing Standard in Iringa region.
Services Provided by Advanced Engineering Solutions:
• Preparation of inception report
• Feasibility Study including preliminary design, economic analysis and cost estimates;
• Preliminary Environmental and Social Impact Assessment (ESIA), Preliminary Resettlement Action Plan (RAP) and survey of properties to be affected;
• Detailed engineering design and cost estimates;
• Detailed ESIA and RAP;
• Preparation of Tender Documents.
Consultancy Services for Feasibility Study, Environmental & Social impact Assessment, Detailed Engineering Design and Preparation of Tender Documents for Construction of a Bridge and its Approach roads to Bypass Mtera Dam and the Babati town Bypass Road (15.5 km) to Bitumen Standard.
Location within the Country: Babati, Manyara and the Dodoma – Iringa Border (Mtera Dam)
Name of the Client: TANROADS – Headquarters
Start date: June 2019
Completion Date: Ongoing
Duration of Assignment: 15 Months
Name of Associated Consultant, if any:Umar Munshi Associates (Pakistan)
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to undertake Feasibility Study, Environmental & Social impact Assessment, Detailed Engineering Design and Preparation of Tender Documents for Construction of a Bridge and its Approach roads to Bypass Mtera Dam and the Babati town Bypass Road (15.5 km) to Bitumen Standard.
Detailed Description of Actual Services provided by your staff:
Advanced Engineering Solution was in charge of:
1.Preparation of inception report
2.Feasibility Study including preliminary design, economic analysis and cost estimates
3.Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected;
4.Detailed engineering design and cost estimates;
5.Detailed ESIA and RAP;
6.Preparation of Tender Documents.
Consultancy Services for Feasibility, Enviromental and Social Study of Shinyanga Water and Sanitation Project
Location within the Country: Shinyanga
Name of the Client: Shinyanga Water and Sanitation Authority
Shinyanga Water and Sanitation Authority
Start date: 10 Feb 2020
Completion Date: 10/10/2020
Duration of Assignment: 9 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The main objective of the consultancy services was to carry out Feasibility, Environmental and Social Study of Shinyanga Water and Sanitation Project
Services Provided by Advanced Engineering Solutions:
2.Preparation of inception report
3. Feasibility Study including preliminary design4.Preliminary Environmental and Social Impact Assessment (ESIA), Development of Preliminary Resettlement Action Plan (RAP) and survey of properties to be affected;
4.Detailed engineering design and cost estimates;
5. Detailed ESIA and RAP;
6.Preparation of Tender Documents
Consultancy Services For Detailed Engineering Design And Preparation Of Tender Documents For Construction Of Mitomoni Bridge And Its Approach Roads (8.2Km) To Bitumen Standard.
Location within the Country: Songea, Tanzania
Name of the Client: TANROADS – Ruvuma
Start date: June 2019
Completion Date: Feb. 2020
Duration of Assignment: 8 Months
Name of Associated Consultant:N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is Detailed Engineering Design and Preparation of Tender Documents for Construction of Mitomoni Bridge and its Approach Roads (8.2Km) to Bitumen Standard. The project also includes design of several drainage structures (box and pipe culverts) along the project approach roads.
Services Provided by Advanced Engineering Solutions:
1.Materials investigation and preparation of materials report
2.Pavement design
3.Detailed engineering Design
4.Preparation of Detailed Drawings
5.Preparation of Detailed Engineering design report
6.Preparation of bill of quantity
7.Preparation of contract documents
Consultancy Services For Feasibility Study, Detailed Engineering Design And Preparation Of Tender Documents For Construction Of Godegode Bridge (80m) And Approaches (6km) Along Mpwapwa – Makutano Jct – Pwaga Jct – Lumuma (Dom/Moro Brd), R478
Location within the Country: Mpwapwa, Tanzania
Name of the Client: TANROADS – Headquarters
Start date: Jan 2020
Completion Date: Ongoing
Duration of Assignment: 6 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to is to carry out Consultancy Services for Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Construction of Godegode Bridge (70M) and approaches (6Km)along Mpwapwa – Makutano Jct – Pwaga Jct – Lumuma (Dom/Moro Brd), R478
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Feasibility Study including preliminary design, economic analysis and cost
estimates;
3.Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected;
4.Detailed engineering design and cost estimates;
5.Detailed ESIA and RAP;
6.Preparation of Tender Documents
Consultancy Services For Supervision Of Upgrading Sumbawanga –Namanyere – Mpanda [245 Km] To Bitumen Standard, Package 4: Sitalike – Mpanda Section [36.9 Km]
Location within the Country: Sumbawanga, Rukwa Region, Tanzania
Name of the Client: TANROADS – Headquarters,
Start date: July 2013
Completion Date: May 2017
Duration of Assignment:24 Months
Name of Associated Consultant, if any: AARVEE Associates Architects Engineers & Consultants PVT LTD [India]
Detailed Narrative Description of Project:
The project involves construction of 36.9 km of road whereby the gravel formed road is being upgraded to bitumen standard. The project also required design review of bridges, drainage structures and road.
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Bridge design review
3.Review of geometrical and profile design
4.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
5.Mix design of stabilized material and cement concrete
6.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
7.Preparation of monthly report
8.Reviewing and approving Contractor’s quality assurance plan
9.Implementation of contractor’s environmental management plane
Consultancy Services for Supervision of Upgrading of Usagara – Kisesa [Mwanza Bypass] Road [16 km] to bitumen standard
Location within the Country: Mwanza, Tanzania
Name of the Client: TANROADS – Headquarters
Start date: July 2013
Completion Date: Extended – 2018
Duration of Assignment: 18 Months
Name of Associated Consultant: AARVEE Associates Architects Engineers & Consultants PVT LTD [India]
Detailed Narrative Description of Project:
The project involves construction of 16 km of road from Kisesa – Usagara the aim being to bypass the Mwanza town so alleviating the traffic congestion. The road is being upgraded from gravel formed road to bitumen standards. The road has numerous hydraulic structures including one Bridge:
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Bridge design review
3.Review of geometrical and profile design
4.Pavement designSupervision of construction of drainage structures such as bridge, box culverts and pipe culverts
5.Review of pavement design6.Mix design of stabilized material and cement concrete
7.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR], surface dressing andPreparation of monthly report
consultancy services for Detailed engineering design of roads 15KM for the real estate development at FUMBA, Zanzibar
Location within the Country: Zanzibar, Tanzania
Name of the Client: AZAM GROUP,
Start date: February/2016
Completion Date: May/2016
Duration of Assignment: 4 Months
Name of Associated Consultant:N/A
Detailed Narrative Description of Project:
The scope of the project: Survey of the Topography of the area and Design of roads required for real estate development at FUMBA, Zanzibar.Features: The DTM of the area around 71Ha, Design of roads (A2, B1, C1 and D1) as well as setting out works for the plots to developed for 2 blocks @ having 10 plots.
Services Provided by Advanced Engineering Solutions:
1.Detailed topographical survey
2.Preparation of DTM
3.Aerial mapping of the area
4.Preparation of surveying reports
Consultancy Services for Carrying out Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Upgrading to Bitumen Standards of Lindi Urban Roads [7.4 km]
Location within the Country: Lindi Tanzaniza
Name of the Client: Lindi Municipal Council
Start date: June 2018
Completion Date: Nov 2018
Duration of Assignment:2 Months
Name of Associated Consultant:
N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is Carrying out Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Upgrading to Asphalt Concrete of Uhuru 0.6 KM, Msonobarini 0.40 KM, Makonde 0. 6KM Roads, Including Mchinga Road Approach and Double Surface Dressing of Rest House 0. 67 KM, Nkuruma 0.43, Amani 0.49, Jamaica1.7KM, Mpilipili 0.78 KM and Eilat 1.62 KM Roads. The Project involved the Preliminary Design of Pavement Design, Geometric Design, Drainage Structures and Preliminary Environmental and Social Impact Assessment.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Preparation of Draft Feasibility Study report including;
3.Preliminary Design Report + Preliminary ESIA + Preliminary RAP
4.Preparation of Final Feasibility Study report including;
5.Preliminary Design Report + Preliminary ESIA + Preliminary RAP
6.Preparation of Draft Final Engineering Design Report including
7.Tender Documents, Detailed ESIA & RAP, Valuation report and cost estimates
Consultancy Services For Detailed Engineering Design, Environmental And Social Impact Assessment And Preparation Of Tender Documents For Upgrading Kibaha Urban Road [11 Km]
Location within the Country: Kibaha – Coast Region
Name of the Client: Kibaha Town Council – Kibaha
Start date: September 2019
Completion Date: March 2020
Duration of Assignment: 5 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The project involved designing of 11 km of urban road. The work also involved Pavement design capable of carrying 1-3 Million Equivalent Standard Axle, geometrical design, traffic analysis, hydraulic /hydrology analysis and design of drainage structures.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Traffic count and traffic analysis
4.Design of all drainage structures
5.Topographical surveying and creation of digital terrain model [DTM] using commercial software
6.Preparation of bill of quantity
7.Preparation of Detailed Engineering design report
8.Preparation of contract documents
Consultancy Services for the Detailed Engineering Design and Preparation of Tender Documents for Rehabilitation of Shinyanga – Bubuki Road paved section [2 km].
Location within the Country: Shinyanga, Tanzania
Name of the Client: TANROADS – Shinyanga,
Start date: January 2014
Completion Date: July 2014
Duration of Assignment: 6 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The project involved designing of 2.0 km of urban road. The work also involved Pavement design capable of carrying 3-10 Million Equivalent Standard Axle, geometrical design, and pavement design capable of carrying 3-10 Million Equivalent Standard axles, traffic analysis, hydraulic /hydrology analysis
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Traffic count and traffic analysis
4.Pavement design
5.Topographical surveying and creation of digital terrain model [DTM] using commercial software
6.Preparation of bill of quantity
7.Preparation of Detailed Engineering design report
8.Preparation of contract documents
Consultancy Services for Carrying out Economical Evaluation, Preliminary Design and Detailed Engineering Design of Ubungo Intersection
Location within the Country: Dar es salaam, Tanzania
Name of the Client: TANROADS – Dar Es Salaam
Start date: November 2013
Completion Date: 04/14
Duration of Assignment: 6 Months
Name of Associated Consultant, if any: Hamza Associate – Egypt (Lead Consultant)
Detailed Narrative Description of Project:
For the purpose of commodious and safe movement of traffic at the then-traffic-bottlenecked Ubungo intersection which connects the lively Mandela and Morogoro roads, Advanced Engineering Solutions in association [as a Sub-Consultant] with Hamza Associate of Egypt was appointed in providing consultancy services for carrying out economical evaluation, preliminary design and detailed engineering design of Ubungo intersection. On April 2014 the required assignment was duly completed to the desired project outcomes.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Geotechnical investigation, the data were used as input for the design of bridge
3.Materials investigation and preparation of materials report
4.Design of flyover bridges [total 8 bridges]
5.Traffic count and traffic analysis
6.Design of steel pedestrian bridge
7.Pavement design
8.Topographical surveying and creation of digital terrain model [DTM] using commercial software
9.Preparation of Detailed Engineering design report
10.Preparation of bill of quantity
11.Preparation of contract documents
Consultancy Service Detailed Engineering Design of Furahisha Pedestrian Flyover composite Bridge and addition of Lane from Furahisha – Ghana in Mwanza region [0.723 km].
Location within the Country: Mwanza, Tanzania
Name of the Client: TANROADS – Mwanza
Start date: Septemberr 2014
Completion Date: December 2014
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
For the purpose of spacious accommodation of traffic along the vital and lively Ghana -Furahisha roadway which forms an integral part of the road to and from Mwanza Airport and Mwanza City Centre, as well as ensuring safety of pedestrians crossing the road with most of them accessing Rock City Mall; Advanced Engineering Solutions was engaged in providing consultancy services for the detailed engineering design and preparation of tender documents for pedestrian bridge and addition lane by widening the pavement so as to increase the number of lanes from two lanes to four lanes forming a dual carriageway road from Ghana -Furahisha roadway. The assignment was duly effectuated to the desired and required outcomes.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Traffic count and traffic analysis
4.Design of steel pedestrian bridge
5 .Pavement design
6.Topographical surveying and creation of digital terrain model [DTM] using commercial software
7.Preparation of Detailed Engineering design report
8.Preparation of bill of quantity
9..Preparation of contract documents
Consulting Services for The Construction Supervision of The Rehabilitation of The Kafue Mazabuka Road (T1) In Southern Province – Lot 2
Location within the Country: Kafue, Zambia
Name of the Client: Road Development Agency
Start date: 2019
Completion Date: 2022
Duration of Assignment: 36 Months
Name of Associated Consultant:
Ethio Infra Engineering PLC in association with Advanced Engineering Solutions and TACT Engineering Group PLC
Detailed Narrative Description of Project:
As the Southern Africa Development Community’s [SADC] North-South Corridor
comprising of six International trunk routes connects Zambia with the neighboring
countries of Zimbabwe, Botswana and Namibia of which Kafue-Mazubuka road is
one them; the Government of the Republic of Zambia has instigated upgrading of
Kafue-Mazubuka road [T1] in Southern Province to bitumen standard for the
effective accommodation of trade and the transportation of International cargo and
bulk commodities between the countries of Zimbabwe, Botswana, Namibia and
South Africa.
The Road Development Agency has appointed Advanced Engineering Solutions, in
association [as a Sub-Consultant] with Ethio Infra Engineering PLC and TACT
Engineering Group PLC in providing consultancy services for the supervision of
upgrading Kafue-Mazubuka road to bitumen standard. Advanced Engineering
Solutions has already geared-up in undertaking the assignment for the successful
realization of the desired project outcomes.
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Bridge design review
3.Review of geometrical and profile design
4.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
5.Review of pavement design
6.Mix design of stabilized material and cement concrete
7.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
8.Preparation of monthly report
9.Reviewing and approving Contractor’s quality assurance plan
Consulting Services For Carrying Out Feasibility Study, Environmental and Social Impact Assessment, Detailed Engineering Design, and Preparation of Tender Documents for upgrading of Mkuyuni – mahina – nyakato road (10 km) – lot 1 and nyakato veta – Buswelu – Mhonze Road (14.2 km) – lot 2 in Mwanza Region to Bitumen Standard.
Location: Mwanza Urban,Nyamagana and ilemela district
Client: Tanroads,Mwanza.
Start date: 6TH JUNE 2021
Completion Date: 6TH JUNE 2022
Duration of the assignment: 12 MONTHS
Detailed description of the assignment:
The objective of the assignment is to carry out Feasibility Study, Environmental and Social ImpactAssessment and Detailed Engineering Design to cover the two roads’ sections with a total of 24.2 kmin Mwanza city.
Detailed Description of Actual Services provided by your staff:
Advanced Engineering Solution was in charge of:
1.Preparation of inception report
2.Feasibility Study including preliminary design, economic analysis and cost estimates
3.Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected;
4.Detailed engineering design and cost estimates;
5.Detailed ESIA and RAP;
6.Preparation of Tender Documents.
Consultancy services for Feasibility Study, Detailed Engineering Design andPreparation of Tender Documents for Upgrading of Isongole II – Kasumulu – Ipyana –Katumbasongwe Regional Road 114.67Km Including Ndembo – Isoko Spur Road6Km to Bitumen Standard.
Location within the Country: Songwe, Tanzania
Name of the Client: TANROADS – Songwe
Start date: July 2021
Completion Date: Ongoing
Duration of Assignment: 8 Months
Name of Associated Consultant: Extreme Engineering Solutions Ltd
Detailed Narrative Description of Project:
The Isongole II-Kasumulu-Ipyana-Katumbasongwe road (114.67km) section is the regional road located in Songwe region running adjacent to Tanzania/Malawi border and joining the Ileje district in Songwe region and Kyela district in Mbeya region.The road starts at Ileje (Isongole round about to Malawi border) and traverse eastwards through Ibungu, Ndembo, Ngana, Kasumulu (lubele) villages and Isoko spur road starts at Ndembo village heads north-west joining Isoko village. The project roads are currently engineered gravel roads. The roads are in fair/poor condition and become semi-impassable at some locations during the rain seasons. The traffic on these roads is suppressed due to the poor condition of the road. However, it is expected that substantial traffic will be generated after upgrading them to bitumen standard
Consultancy Services For Economic Study Environmental & Social Impact Assessment, Detailed Engineering Design &Preparation Of Tender Document For Singida Bypass Road (46.0km) To Be Financed Through Development Roads Fund
Location within the Country: Singida, Tanzania
Name of the Client: TANROADS – Headquarters
Start date: Jun 2020
Completion Date: Ongoing
Duration of Assignment: 8 Months
Name of Associated Consultant: N/A
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to is to carry out Economic study Environmental and social impact assessment detailed engineer design and preparation of tender documents for Singida bypass road (46.0KM)
.
.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2. Study including preliminary design, economic analysis and cost estimates;
3.Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected;
4.Detailed engineering design and cost estimates;
5.Detailed ESIA and RAP;
6.Preparation of Tender Documents.
Consultancy Services for Supervision of Construction of Investment sub-projects in Arusha – Municipality under the Tanzania Strategic Cities Project Package 1: Rehabilitation of CBD Roads 30km, Construction of Bondeni drain and Installation of Solar powered traffic Signal.
Location within the Country: Arusha, Tanzania
Name of the Client: Arusha Municipal Council. Financed by Word Bank
Start date: November 2011
Completion Date: November 2013
Duration of Assignment: 24 Months
Name of Associated Consultant:
SNC Lavalin and MMK services
Detailed Narrative Description of Project:
The project provides for new construction/upgrading/ rehabilitation of approximately of 30 km of roads to asphalt concrete standard, including vertical and horizontal alignment design, pavement design, bridges construction, drainage structures, street light and traffic lights, construction of 1 km of lined storm water drains, including alignment and structural designs for flood control in the central business district, Rehabilitation and expansion of dumpsite, including creation of additional cells, construction 1 km inner road, storm water and leachate stabilization pond and acquisition of solid waste management equipment
Services Provided by Advanced Engineering Solutions:
1.Preparation and approval of Quality control and quality assurance plan
2.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
3.Review of pavement design
4.Mix design of stabilized material, asphalt concrete, cement concrete
5.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete
6.Preparation of monthly report
7.Reviewing and approving Contractor’s quality assurance plan
8.Implementation of contractor’s environmental management plan
Consultancy Services for Detailed Engineering Design and Preparation of Tender Documents for Service Roads to bitumen Standard, Traffic and street Lights, and Pedestrian Overhead Bridge along Mwenge – Tegeta Road along New Bagamoyo Road [12.9 km].
Location within the Country: Dar Es salaam, Tanzania
Name of the Client: TANROADS – Dar Es Salaam
Start date: August. 2013
Completion Date: 4 april 2014
Duration of Assignment: 6 Months
Name of Associated Consultant:
Technplan – Italy (Associate Consultant)
Detailed Narrative Description of Project:
For the purpose of spacious accommodation of traffic along the vital and lively New
Bagamoyo road as well as ensuring safety of pedestrians crossing the road,
Advanced Engineering Solutions in association [as a Sub-Consultant] with Technplan
of Italy was engaged in providing consultancy services for the detailed engineering
design and preparation of tender documents for service roads to bitumen standard,
traffic and street lights, and pedestrian overhead bridge along Mwenge – Tegeta
road along New Bagamoyo road [12.9 Km]. The assignment was duly effectuated to
the desired project outcomes.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Geotechnical investigation, the data were used as input for the design of pedestrian bridge
3.Materials investigation and preparation of Materials & Pavement design report
4.Traffic count and traffic analysis
5.Design of actuated traffic lights
6.Design of steel pedestrian bridge
7.Topographical surveying and creation of digital terrain model [DTM] using commercial software
8.Preparation of Detailed Engineering design report
9.Preparation of bill of quantity
10.Preparation of contract documents
Consultancy Services for Carrying out Feasibility Study, Detailed Engineering Design and Preparation of Tender Document for Expansion of Mabatini Box Culvert 3×5.0 m x 2.5 m in Mwanza Region.
Location within the Country: Mwanza, Tanzania
Name of the Client: TANROADS – Mwanza
Start date: Sept 2017
Completion Date: July 2018
Duration of Assignment: 6 Months
Detailed Narrative Description of Project:
As an integral part of the Government [of the United Republic of Tanzania] strategy to accelerate the development of its road network as well as its associated facilities for the facilitation of socio-economic development, TANROADS Mwanza Regional Manager’s Office appointed Advanced Engineering Solutions for the provision of consultancy services for the expansion of Mabatini box culvert with the intention of improving the capacity of the box culvert so as to deter the repeatedly occurrences of floods as well as enhancing mobility of the people living within Mwanza Region as well as nearby interconnected Regions. On July 2018 the assignment was duly completed to the required project outcomes.
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Materials investigation and preparation of materials report
3.Pavement design
4.Detailed engineering Design
5.Preparation Detailed drawings
6.Preparation of Detailed Engineering design report
7.Preparation of bill of quantity
Preparation of contract documents
Consultancy Services for Supervision of Construction of Kilombero Bridge [384 m] and its approach roads [9.142 km] along Ifakara – Mahenge Trunk Roads
Location within the Country: Morogoro , Tanzania
Name of the Client: TANROADS – Headquarters
Start date: March 2013
Completion Date: Aug 2017
Duration of Assignment: 24 Months
Name of Associated Consultant:
AARVEE Associates Architects Engineers & Consultants PVT LTD [India]
Detailed Narrative Description of Project:
The project involves construction of two bridges the main bridge being 384 m and minor relief bridge of 120 m and construction of approach road of 9.142 km. The project also required design review of bridges and road. The review of design includes review of bridge design, review of the road design which includes vertical and horizontal alignment design, pavement design, drainage structures, structural designs for flood control structure,
Services Provided by Advanced Engineering Solutions
1.Preparation and approval of Quality control and quality assurance plan
2.Bridge design review
3.Supervision of construction of drainage structures such as bridge, box culverts and pipe culverts
4.Review of pavement design
5.Mix design of stabilized material and cement concrete
6.Approval of all construction materials such subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
7.Preparation of monthly report
8.Reviewing and approving Contractor’s quality assurance plan
Consulting Services for Detailed Design and Construction Supervision of fourteen 14 warehouse and outdoor support Storage Facilities
Assignment name:
Consulting Services for Detailed Design and Construction Supervision of fourteen 14 warehouse and outdoor support Storage Facilities
Location within the Country: Tanzania
Name of the Client: TANPAC
Address:
Secretary
Ministerial Tender Board,
Ministry of Agriculture
University of Dodoma,
School of Humanities,
Block 9, Ground Floor, Room No. I 121,
P.O. Box 2182, 40487 DODOMA, TANZANIA
E-Mail ps@kilimo.go.tz
Start date:
November 2019
Completion Date:
October 2020
Name of Associated Consultant, if any:
AV Consult P.O box 33213, Alpha crown electrics ltd, p.o box 32197, Turner and Townsend plot 21 Yusuf Lule Road Kampala.
Detailed Narrative Description of Project:
The Main objective of these consultancy services is to undertake design and supervision for the Construction of fourteen (14) storage warehouses and outdoor supporting facilities for different selected sites in Tanzania Mainland (12) and Zanzibar (2). This will include undertaking situational analysis of the proposed sites and carrying out the design and supervision of construction works.
Detailed Description of Actual Services provided by your staff:
Advanced Engineering Solution is in charge of:
- Preparation of the inception report
- Feasibility Study including preliminary design, economic analysis and cost
estimates; - Preliminary Environmental and Social Impact Assessment (ESIA), Development
of Preliminary Resettlement Action Plan (RAP) and survey of properties to be
affected; - Detailed engineering design and cost estimates;
- Detailed ESIA and RAP;
- Preparation of Tender Documents.
Consultancy Services For Detailed Engineering Design and Construction Supervision For Rejuvenation Of Songosongo Runway Pavement (1.05 Km Runway).
assignment name: Consultancy Services For Detailed Engineering Design and Construction Supervision For Rejuvenation Of Songosongo Runway Pavement (1.05 Km Runway).
Location within the Country: SongoSongo Island
Name of the Client: PanAfrican Energy
Address: Dar-es-salaam
Start date
[Month/year]: Feb 2016
Completion Date: Aug 2016
Detailed Narrative Description of Project:
Advanced Engineering Solutions was engaged by the PanAfrican Energy to carry out a study, Design and supervision for a suitable rejuvenation remedial work to be carried out at the Songosongo runway so as to ensure that the runway is complying with the requirements of ICAO as well as the aviation regulation as set out by TCRA which is an organ which is monitoring he aviation industry in Tanzania.
The runway was 1,050 m long x 18.50m wide.
Detailed Description of Actual Services provided by your staff:
Advanced Engineering Solution is in charge of:
Preparation of inception report
Materials investigation and preparation of materials report
Pavement design
Detailed engineering Design
Construction supervision
Preparation of Detailed Engineering design report
Preparation of bill of quantity
Preparation of contract documents
Consultancy Services for Rehabilitation and Upgrading of Zanzibar Airport.
Assignment name: Consultancy Services for Rehabilitation and Upgrading of Zanzibar Airport.
Location within the Country: Zanzibar
Name of the Client: Ministry of Communication and Infrastructure – Zanzibar
Address: P.O Box 260 Zanzibar
Start date
[Month/year]: 03/12
Completion Date:
09/13
Narrative Description of Project: the project provides for the rehabilitation of the existing 2460 m runway and extension of the runway by 560 m extending it to the total length of 3200 m. The pavement width to be upgraded to 60 m comprising 45 m of the carriageway and 15 m of shoulder rehabilitation involved placing 60 mm of binder course and 40 mm of wearing course. The airport is upgraded to conform to code 4E in line with ICAO requirements.
Description of Actual Services provided by your staff:
Advanced Engineering Solution was in charge of:
- Preparation and approval of Quality control and quality assurance plan
- Detailed engineering survey for quantity computation as well as quality control of checking location and elevations of runway, taxiways and apron [X, Y, Z]
- Geotechnical investigation for the design of the new parallel taxiways
- Implementation of Contractor’s quality control plan
- Review of pavement design
- Asphalt concrete mix design
- Geometrical design review and improvement for the geometrical features of the runway and taxiways.
- Preparation of various technical reports and correspondences including claims and value engineering proposals.
- Preparation of monthly report
- Management of laboratory which includes management of laboratory tests and field tests such as field density, concrete quality control test etc.
Consultancy Services for Rehabilitation and Upgrading of Bukoba Airport.
Assignment name: Consultancy Services for Rehabilitation and Upgrading of Bukoba Airport.
Location within the Country: Kagera Region
Name of the Client: Tanzania Airport Authority
Address: P.O Box 3013 Dar Es Salaam
Start date
[Month/year]: 11/11
Completion Date: 11/13
Narrative Description of Project: the project provides for new construction/upgrading/rehabilitation of the existing runway by placing 250 mm of the bituminous bound base, 120 mm of binder course and 45 mm of marshal asphalt wearing course. The airport is being upgraded from gravel to bituminous pavement and will be upgraded to CODE 3E in line with ICAO standards. The width of the airport pavement is 30 m. In addition to that, the project also involves the construction of the new terminal building, construction of a new apron, construction of subsoil drainage, and provision of electrometrical and mechanical components/art in the terminal building.
Description of Actual Services provided by your staff:
Advanced Engineering Solution was in charge of:
- Preparation and approval of Quality control and quality assurance plan
- Detailed Engineering survey and cross-sectioning of the runway for computation of the quantity
- Geotechnical investigation before terminal building construction
- Review of pavement design
- Asphalt concrete mix design
- Geometrical design review and improvement for the geometrical features of the runway and taxiways.
- Preparation of various technical reports and correspondences including claims and value engineering proposals.
- Carrying out detailed surveying for setting out the purpose as well as documenting all features for preparation of as-built drawings.
- Preparation of monthly report
- Reviewing and approving the Contractor’s quality assurance plan
Consultancy services for Supervision of construction of Passengers terminal III complex and associated Works & facilities at Julius Nyerere International Airport
Assignment name:
Consultancy services for Supervision of construction of Passengers terminal III complex and associated Works & facilities at Julius Nyerere International Airport
Location within the Country: 
Dar Es Salaam region
Name of the Client: Tanzania Airport Authority [TAA]
Address: P.O Box 18000 Dar Es Salaam
Start date
[Month/year]: 07/13
Completion Date: May 2020
Narrative Description of Project: the project involves the construction of passenger terminal III, the construction of a taxiway and a new apron.
Description of Actual Services provided by your staff:
Advanced Engineering Solution is in charge of:
- Preparation and approval of Quality control and quality assurance plan
- Design review of taxiway pavement, apron, terminal building
- Supervision of construction of drainage structures
- Review of pavement design
- Mix design of stabilized material and cement concrete
- Approval of all construction materials such as subgrade [G7 and G15], stabilized subbase [C1], crushed base [CRR] and Marshal asphalt concrete.
- Preparation of monthly report
- Reviewing and approving the Contractor’s quality assurance plan
Implementation of contractor’s environmental management plan
Consultancy Services for Supervision of Rehabilitation and Upgrading of Kigoma and Tabora Airports
Assignment name:
Consultancy Services for Supervision of Rehabilitation and Upgrading of Kigoma and Tabora Airports
Location within the Country:
Kigoma and Tabora, Tanzania
Name of the Client: Tanzania Airports Authority
Address:
Tanzania Airports Authority
P.O Box 18000 Dar es Salaam, Tanzania
Start date
[Month/year]: Sept/2017
Completion Date: Ongoing
Detailed Narrative Description of Project:
The main objective of the project is to carry out Supervision of proposed rehabilitation and upgrading works at Kigoma and Tabora Airports. The assignment includes supervision of the works to final completion including the defects liability period.
Detailed Description of Actual Services provided by your staff:
Advanced Engineering Solution is in charge of:
- Provide continual contract supervision services up to the completion dates.
- Quality Control
- Check and approve the contractors setting out of the works
- Measure or verify quantities of completed work and prepare monthly interim payment valuations, based on provisional quantities for progress payment approval by TAA.
- Provide continuous liaison with TAA or its appointed representative
- Documentation of site reports/activities
- Record all claims and submit timely recommendations thereon for consideration by TAA
- Management of ESMP in coordination with NEMC and all relevant parties
- Ensure regular and effective reporting and information sharing with TAA
- Check and compile as built drawings prepared by the Contractor
Preparation of supervision reports
Provision Of Consultancy Service On Public Private Partnerships With Case Study Of The Transport Sector For The Ministry Of Finance
Provision Of Consultancy Service On Public Private Partnerships With Case Study Of The Transport Sector For The Ministry Of Finance
Location within the Country: Dar Es Salaam, Tanzania
Name of the Client: Tanzania Ministry of finance
Start date: Aug 2015
Completion Date: March 2016
Duration of Assignment: 6 Months
Name of Associated Consultant: SIRWAY LIMITED
.
Detailed Narrative Description of Project:
With due regard to the fact that the Government of the United Republic of Tanzania
recognizes the role of private sector in bringing about socio-economic development
through investments in line with the established Public-Private Partnership [PPP]
frameworks which provide the important instruments for attracting investments
through PPPs constituting a cooperative venture built on the synergy of expertise of
each partner that best meets clearly defined public needs via the most appropriate
allocation of resources, risks and rewards; Advanced Engineering Solutions, in
association [as a Sub-Consultant] with SIRWAY LIMITED was engaged to provide
consultancy services to the Ministry of Finance on Public Private Partnerships with
case study of the Transport Sector. The assignment was duly realized to the desired
and required project outcomes..
Services Provided by Advanced Engineering Solution:
1.Economic analysis
2.Coordination of project activities as a local consultant
3.Project management
4.Economic study
Consultancy Services For Feasibility Study, Detailed Engineering Design And Preparation Of Tender Documents For Construction Of Suguta And Mwanjiri Bridges And Its Approach Roads To Gravel Standard (1.5km) Pandambili – Mlali – Ng’ambi Regional Road, R.470
Consultancy Services for Feasibility Study for Construction of Suguta and Mwanjiri Bridges:
LOCATION: Dodoma, Tanzania
Name of the Client: TANROADS, Dodoma
Start Date: August,2021
Completion Date: Ongoing
Duration of Assigment:6
MonthsName of Associated Consultant-N/A
Detailed Narrative Description of Project:
The key objectives of this assignment are to carry out Consultancy Services for Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Construction of Suguta and Mwanjiri Bridges and Its Approach Roads to Gravel Standard (1.5km) Pandambili – Mlali -Ng’ambi Regional Road, R.470
Services provided by Advanced Engineering Solution:
1 Preparation of Inception Report
2 Study, Including preliminary design, economic analysis and cost estimates
3 Preliminary Environmental and Social Impact Assessment (ESIA), Development ofPreliminary Resettlement Action Plan (RAP)and survey of properties to beaffected
4 Detailed Engineering design and cost estimates
5 Detailed ESIA, Valuation and RAP report6 Preparation of Tender Documents
Consultancy Services For Feasibility Study, Environmental And Social Impact Assessment, Detailed Engineering Design And Preparation Of Tender Documents For Upgrading Of Same – Kisiwani – Mkomazi Road (100.5 Km) To Bitumen Standard.
Location within the Country: Kilimanjaro, Tanzania
Name of the Client: TANROADS – Kilimanjaro
Start date: June 2018
Completion Date: October 2020
Duration of Assignment:28 Months
Name of Associated Consultant: ACC LTD
Detailed Narrative Description of Project:
The Main objective of these consultancy services are divided into two phases;
Phase 1: Feasibility Study including the Preliminary Design, Cost Estimates, Preliminary Environmental & Social Impacts, Economic Evaluation and Development of Preliminary Resettlement Action Plan
Phase 2: Detailed Engineering Design, including Detailed Environmental and Social Impact Assessment, development of Resettlement Action Plan and Preparation of Bidding Documents
Services Provided by Advanced Engineering Solutions:
1.Preparation of inception report
2.Preparation of Draft Feasibility Study report including;
3.Preliminary Design Report + Preliminary ESIA + Preliminary RAP
4.Preparation of Final Feasibility Study report including;
5.Preliminary Design Report + Preliminary ESIA + Preliminary RAP
6.Preparation of Draft Final Engineering Design Report including
.Tender Documents, Detailed ESIA & RAP, Valuation report and cost estimates
Consultancy Services For Feasibility Study, Detailed Engineering Design And Preparation Of Tender Documents For Construction Of Kelema Maziwani Bridge And Its Approach Roads To Gravel Standard (1.5km) Along Kondoa – Bicha Regional Road, R462
LOCATION: Dodoma, Tanzania
Name of the Client: TANROADS, Dodoma
Start Date: August,2021
Completion Date: Ongoing
Duration of Assigment:6 Months
Name of Associated Consultant-N/A
Detailed Narrative Description of Project: The key objectives of this assignment are to carry out Consultancy Services for Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents for Construction of Kelema Maziwani Bridge and its approach roads (1.5 km) along Kondoa – Bicha – Dalai Regional Road (R462) to gravel standard
Services provided by Advanced Engineering Solution:
1 Preparation of Inception Report
2 Study, Including preliminary design, economic analysis and cost estimates
3 Preliminary Environmental and Social Impact Assessment (ESIA), Development of Preliminary Resettlement Action Plan (RAP) and survey of properties to be affected
4 Detailed Engineering design and cost estimates
5 Detailed ESIA, Valuation and RAP report
6 Preparation of Tender Documents
Consulting Services For Feasibility Study, Detailed Engineering Design And Preparation Of Tender Documents For Upgrading Of Bariadi – Kisesa – Mwandoya – Ng’oboko – Mwanhuzi – Sibiti – Nduguti – Iguguno Section (89km) To Bitumen Standard
Location within the Country: Singida, Tanzania.
Name of the Client: TANROADS – SINGIDA
Start date: 27 October 2021
Completion Date: Ongoing
Duration of Assignment: 12 Months
Name of Associated Consultant: M/s Howard Consulting Limited
Detailed Narrative Description of Project:
The Mkalama – Iguguno Road Section (89.0 Km) starts at Chemchemi Village in the Mkalama area along Serengeti Southern Bypass (currently design ongoing) towards Mkalama centre and passes through various Villages including Ibaga, Mkalama, Igonia, Ikungu, Gumanga, Nduguti
township, Mazinga, Ishenga, Kinyangiri and ends at Iguguno centre where it joins with Singida – Nzega road (T003). The last 2.5 km at Iguguno is a paved section with a DSD surface constructed as a spur road connecting T003 and Iguguno centre. Bypass to Singida–Shelui Trunk Road in Singida Region. All road section is in the Singida region. The road crossed several major bridges most of them experienced overtopping.
The subject project road section passes through areas with potential assorted economic opportunities such as agriculture, livestock and minerals (Gold) at Igonia Village. Further, the road traverses through the area with lots of social activities such as; schools, historical buildings
(Ancient/Antique Monument which might be under National/World heritage), hotels and small shops. At Mkalama village the road passes at the important German historical buildings (Mkalama Ruins) between the two buildings which were used as guard posts during German. However, these economic potentials are not fully exploited due to the lack of reliable road transport infrastructure. At the major village centres of Ibaga, Mkalama, Gumanga and Nduguti where the construction corridor is constrained, a bypass may need to be considered
Services Provided by Advanced Engineering Solutions:
1 Preparation of inception report
2 Study including preliminary design, economic analysis and cost estimates;
3 Preliminary Environmental and Social Impact Assessment (ESIA), Development of Preliminary Resettlement Action Plan (RAP) and survey of properties to be affected;
4 Detailed engineering design and cost estimates;
5 Detailed ESIA and RAP;
6 Preparation of Tender Documents.
Consultancy Services For Supervision Of Roads Upgrading To Bitumen Standard (8km) Within Bukoba Municipality.
Consultancy Services For Supervision Of Roads Upgrading To Bitumen Standard (8km) Within Bukoba Municipality.
Location within the Country: Bukoba, Tanzania
Name of the Client: Bukoba Municipal Council
Start date: Oct. 2017
Completion Date: June 2020
Title of Associated Consultant: N/A
Detailed Narrative Description of Project:
The scope of assignment consists of (but is not limited to) design review and supervision of roads upgrading to bitumen standard for the total length of 8km which
will eventually improve urban infrastructure and settlement
Services Provided by Advanced Engineering Solutions:
1. Supervision of the works contract to ensure that the works comply with the approved design,
2. drawings, specifications, conditions of contract and sound engineering practice;
3. Approval of Contractor’s working drawings
4. Preparation and submission of monthly progress report
5. Preparation of final construction report and as-built drawings of all completed works;
6. Preparation of the project completion report;
7. Supervision of maintenance activities during the defects liability period